BobVitale? - 08 Aug 2007
Status |
Stage |
Date |
What |
Notes |
done |
1 |
July 24-25 |
Move Susan Leach to empty faculty office in E2 |
temp for construction |
done |
2 |
July 25-27 |
Move Vanessa to cube in 298 |
temporary for construction |
underway |
3 |
July 25-27 |
Relocate faculty services bookcases and material to E2-298 kitchen area. Disassemble cubes against E2-298B wall |
temp for construction |
wait for date |
|
?? |
Hang sheet plastic around doorway wall area |
to keep dust down for rest of office |
|
|
|
Ready for Area for Construction Phase I start |
|
|
|
|
underway |
4 |
Aug 8-10 |
Move Carolyn Steven & Stewart to cubes near faculty services counter |
Permanent |
|
|
|
Cubes cleared for Katie, Jolinda and Jodie from main construction area in E2-298 East |
|
|
5 |
Aug 15-17 |
Move Jodie to cube in E2-298 West |
temporarily for construction |
|
5 |
Aug 15-17 |
Move Katie and Jolinda to cubes in E2-298 West |
permanent |
|
6 |
Aug 20-24 |
Disassemble cubes in E2-298 East |
store in E2-280? may need for staff |
|
|
|
Area for new offices now clear. |
|
|
|
|
|
|
|
TBD |
Construction Phase I start |
Doorway & counter for faculty services |
|
|
TBD |
Electrical Data Relocation |
Cyclops Electric sub of Rich Denton |
|
|
|
Doorway Installation |
Rich Denton |
|
|
TBD |
Lockset Installation |
UCSC Lockshop |
|
|
|
|
|
|
TBD |
Construction Phase II start |
New offices in E2-298 East |
|
|
Aug 29-31 |
Wall installation |
Mark King of Advance Installation Services |
|
|
TBD |
Electrical Connection and Data Installation |
Cyclops Electric sub of Rich Denton |
|
|
TBD |
HVAC modification |
Rich Denton |
|
|
TBD |
FireSprinkler? Mods |
TBD - Dean Ricker |
|
|
TBD |
Lockset Installation |
UCSC Lockshop |
|
|
|
|
After Phase I Construction -----
(all dates TBD)
PostConstruction? 1-1: Assemble faculty services counter
PostConstruction? 1-2: Move Carolyn Stephens into 298B
PostConstruction? 1-3: Move Vanessa to faculty services counter
After Phase II Construction --------
PostConstruction? 2-1: Construct furniture in new offices.
PostConstruction? 2-2: Move Tracy and Susan into offices 298-K, 298-I
PostConstruction? 2-3: Move Pat in 298-G (Tracy's old office)
PostConstruction? 2-4: Move Meridith into 298-D (Pat's Old Office)